How to prove a newly installed or repaired machine is safe and runs to spec before handover, and how to take a machine out of service, record it and preserve what is kept.
What the exam tests here
Five exam questions come from this task. Expect the test-run preparation steps, why every safety device must pass before handover, baseline readings at start-up, the order of decommissioning (lockout first, records last), what the CMMS record shows afterward, and how to preserve stored equipment and spares. Test-run prep and the decommissioning order are the highest-yield.
Commissioning proves that a newly installed or repaired machine is safe and runs to its specifications before production takes it. Work from a checklist built from the maker's manual, the drawings and the regulations.
Mechanical and fluid-power checks
Safety components
Watch out
A machine that runs well but has one dead stop, guard or interlock is not ready. Every safety device passes before handover.
Prepare before power goes on:
Then run it in stages:
Exam tip
No power until the paper and hand checks are done: release signed, checklists finished, lines flushed, guards fitted, rotation checked by hand, crew warned.
Run-in (break-in) is the first stretch of running, while new parts bed in and settle. Watch closely and adjust as you go.
Baseline readings capture the new machine's normal running condition:
Exam tip
Start-up readings are the machine's baseline. Every later vibration survey is judged against them.
Production takes the machine only when every checklist item has passed and the paperwork is complete. The handover package holds:
In the CMMS:
Exam tip
No handover until the checklist is complete and signed. These records start the machine's history.
Decommissioning is the formal process of taking equipment out of service, whether it will be scrapped, sold, moved or stored. Plan it from the maker's manual, the drawings, the SDSs and the site's environmental rules.
Isolation and entry
The CMMS record
Watch out
Decommissioning order: lock out → drain → clean → dismantle and remove → sort the materials → record. Lockout first, paperwork last.
Exam tip
Before breaking old gaskets or lagging, check the asbestos survey; trained abatement workers remove what it lists. Suspect material it doesn't cover, or contamination such as oil-soaked soil under a pit: stop, don't disturb it, and report it. Never cover it over or wash it away.
Stored machines and spares rust from condensation, and parts that never turn lose their oil film. Preserve them, and give them PM tasks so the turning and checks get done.
Gearboxes and machines
Spare parts
Exam tip
A stored gearbox gets preservative oil, sealed openings, rust preventive on bare steel, a monthly turn by hand, and a tag to drain and refill before start-up.
The full study guide covers every block of the 433A Industrial Millwright exam, with practice questions and a timed mock exam.